Updates


Haggitt St & Windsor Tce
The Contract involves the renewal of 680 meters of water main and 690 meters of new rider main along Haggitt Street, Windsor Terrace.

(Last Updated: 23/05/2018)

Feilding Wastewater Treatment Plant
The Feilding Wastewater Treatment Plant (FWWTP) was constructed circa 1967. The two sedimentation tanks at the treatment plant are approximately 50 years old and at the end of their originally intended service lives.Weekly update: Hand rain for tank 1 and 2 are 98% complete. Tank 2 has been re-commissioned.

(Last Updated: 23/05/2018)

Derby Street Stormwater
The installation of a new Stormwater line from McCorkindale Street, down Derby Street to the Makino Stream. The new stormwater line will allow the residential development at Wescombe Grove (33 additional lots) to be connected to the new line and reduce the pressure on the existing stormwater network.Weekly update: Steady progress is being made along Derby Street. 365 meters of new stormwater main has been installed. The stormwater main is now approximately 3.0 meters deep. Permanent surface reinstatement has taken place to halfway between Prince Street and North Street.

(Last Updated: 23/05/2018)

East Street Sewer Relining
The existing sewer in East Street needs rehabilitation and the most cost effective method is trenchless relining. This allows relining of the sewer main without excavation or at least with minimal excavation.Weekly update: Schedule in for the remainder of East Street to be completed in June 2018

(Last Updated: 23/05/2018)

Queen Street Stormwater
The stormwater pipe in Queen Street has been identified as needing rehabilitation. The option we have originally chosen was to reline the existing stormwater pipe using a resin that is non-harmful to the environment. Unfortunately the material is no longer available so alternative options are being investigated.Weekly update: The contracting engineer will provide a new proposal of both open trench and alternative reline options due to the original relining materials being no longer available.

(Last Updated: 23/05/2018)

Port Street Stormwater/Water/Sewer
Port Street East is an integral part of the Precinct 4 urban development. There is currently a high development demand for this area.Weekly update: Water - Progress on this stage is slow this week and no significant changes from previous week. The watermain has been completed up to Pharazyn Street and lateral connections are being made to individual properties. All watermain crossing the road has been completed. Stormwater – Installation of the stormwater continues a steady approach to the intersection of Churcher Street and Port Street. Sewer – Installation of the sewer on Churcher Street continues towards the intersection of Port Street.

(Last Updated: 23/05/2018)