Churcher Street - 3 Waters Upgrade

churcher.jpg

The Contract involves the construction of approximately 324m of stormwater drainage, 440m of wastewater drainage, 389m of watermains and approximately 395m of water ridermain. The project is part of the development of the precinct 4 growth.

The contract was awarded to Higgins Contractors Limited last year in October and work is well underway. At the moment about 200m of stormwater pipe has been laid and approximately 100m of ridermain on the eastern side of the road. Work is expected to be completed by June 2020.

 

Timeline: completion June 2020

Status: Under Action