Latest Update - 17 July 2024

This week a section of the bridge was cleaned and prepared ready for the installation of 22 new hangers.

Unfortunately, the process to galvanise the hangers has been delayed due to technical problems at the galvanising plant in Auckland.  The hangers are expected to be delivered by the end of the week.

Until the hangers are delivered to site, the bridge will be open to vehicles with a weight limit of 6 tonnes, at a speed of 10 km per hour, with one vehicle crossing at a time travelling central to the bridge.