LGOIMA Request Details: LG1838
Date received: 08/04/2019
Requested information: MDC Construction Project Enquiries
Status: Complete
Date responded: 11/04/2019
Response:
Project Name Response
Kitchener Park Restoration Work on Kitchener Park is ongoing maintenance of the reserve, and is not considered a project.
Skate Park The skate park project is currently in its design phase, and design work has commenced. Council will be submitting consents for this project, and an architect has been appointed. Council will not be inviting tenders for this project, and works are programmed for completion by July 2020.
Manawatu Stormwater Upgrade - May I know the current status of this project?
Underway
- Are designs underway for this? Or is this on hold?
Yes & no
- Will you be submitting any consents for this?
Yes
- Are there any design engineers on board?
Yes
- Will you be inviting tenders for this one?
Yes
- Would you happen to know when will works start? And when is this due completion?
Already underway and completion this financial year
Turners Road Extension
The project is currently in its Pre-Implementation Phase. WSP-Opus have been engaged to undergo survey and design. Council is required to obtain a resource consent for this project under the requirements of the RMA.
When design, land acquisition and consenting processes are complete, tenders will be called for the construction phase.
Work start date and forecasted completion are currently unknown.
Te Kapua Bridge Work was completed in 2017. The project involved culvert re-lining.
City To Sea Rail Trail The Manawatu District Council Long Term Plan 2018-28 states ‘Although Council has not allocated any funding to this project, it is supportive of the proposal to construct a cycleway from the City (Palmerston North) to the Sea (Himatangi). Requests for funding will be reconsidered in the future as the plans become finalised.’
Kitchener Park Restoration Work on Kitchener Park is ongoing maintenance of the reserve, and is not considered a project.
Skate Park The skate park project is currently in its design phase, and design work has commenced. Council will be submitting consents for this project, and an architect has been appointed. Council will not be inviting tenders for this project, and works are programmed for completion by July 2020.
Manawatu Stormwater Upgrade - May I know the current status of this project?
Underway
- Are designs underway for this? Or is this on hold?
Yes & no
- Will you be submitting any consents for this?
Yes
- Are there any design engineers on board?
Yes
- Will you be inviting tenders for this one?
Yes
- Would you happen to know when will works start? And when is this due completion?
Already underway and completion this financial year
Turners Road Extension
The project is currently in its Pre-Implementation Phase. WSP-Opus have been engaged to undergo survey and design. Council is required to obtain a resource consent for this project under the requirements of the RMA.
When design, land acquisition and consenting processes are complete, tenders will be called for the construction phase.
Work start date and forecasted completion are currently unknown.
Te Kapua Bridge Work was completed in 2017. The project involved culvert re-lining.
City To Sea Rail Trail The Manawatu District Council Long Term Plan 2018-28 states ‘Although Council has not allocated any funding to this project, it is supportive of the proposal to construct a cycleway from the City (Palmerston North) to the Sea (Himatangi). Requests for funding will be reconsidered in the future as the plans become finalised.’