LGOIMA Request Details: LG2367

Date received: 14/07/2025

Requested information: Details of construction projects over $10M completed in the last 5 years

Status: Complete

Response:

In the last 5 years, we have had only one project with a value exceeding $10 million. The details are as follows: 

The approved total budget was $12.5 million, which included the contract build, professional services, and contingency. The project was completed within budget.  

 

Client Name Manawatū District Council 
Contract / Project Name Feilding Public Library – Strengthening and Modernisation (SAM) Project 
Name of Design Consultants Architecture + (note A+ subcontracted work to other specialists as required but MDC worked with A+). 
Design Spend 

$1,206,067.16  

 

Name of Contractor Alexander Construction Central Ltd 
Contract Type NZ3910:2013 
Initial Contract Price $8,624,777.76  
Final Contract Price $10,222,695.82  
Contract Start Date 26 August 2022 
Due Date for Completion 18 April 2024 
Date of Practical Completion 22 July 2024 
Scope overview statement 

The project will include the required strengthening, modernising and extension of the existing library building. The modernising of the building includes both the interior and exterior. The new layout of the building will include the capability to be a multi-purpose facility that can cater for a wider range of activities that complement the library functions. 

The project will also investigate the potential of introducing environmentally sustainable building improvements. 

The project will also manage the temporary relocation of library staff and library services to maintain functions.