Manawatū District Council

Decision number: MDC 25-28/327 (PX)

Meeting date: 22/07/2026

Subject: Tender Award Recommendation - Community Resilience Programme (Public Excluded)

Resolution:

1. That Council award the design and construction contract for the Community Resilience Programme to Tū Mai Rā Energy General Partner Limited for the sum of $621,764.17 plus GST.

2. That Council approve a project contingency amount of $40,235.82 plus GST utilised only upon the written approval of the Engineer of the Contract.

3. That Council note the project is jointly funded through the Energy Efficiency and Conservation Authority (EECA) and Central Energy Trust (CET) funding and that all works are required to be completed by 30 December 2026.

Moved by: Cr Sam Hill

Seconded by: Cr Colin Dyer

Result: Carried (12-0)

For:
Mayor Michael Ford Cr Bridget Bell Cr Shelley Dew-Hopkins Cr Rob Duindam Cr Colin Dyer Cr Grant Hadfield Cr Sam Hill Cr Raewyn Loader Cr James McKelvie Cr Jerry Pickford Cr Andrew Quarrie Cr Alison Short

Against:

Abstained: